Switch to LED: Is a Simple Swap Really Simple?

  • Ningenryoku Course, MJIIT
  • Mission statement for the group exercise

The scene: a launch with LED headlamps

  • X Motors updates its Model K
  • LED headlamps in all regions
  • Launch on October 1, 2027, called Day D
  • R&D center: just swapping the light source
2 / 28

The twist and the clock

  • Production lines must keep running
  • Quality must not drop
  • Today: Friday, April 16, 2027
  • Worldwide launch is 24 weeks away
24 weeksToday:April 16, 2027Day D:October 1, 2027
3 / 28

The mission: launch on Day D without stopping the lines

  • Launch the updated Model K with LED headlamps
  • All regions, October 1, 2027 (Day D)
  • Switch from the old model to the updated model
  • Do not stop the running production lines
  • Do not lower quality
4 / 28

Your room's task: one sheet for the coordination meeting

  • Your room prepares for next week's all-party coordination meeting
  • Take the positions of the plants, R&D center and Y Electrical
  • Sort out what must be decided, by when and by whom
  • Put one path on one sheet
  • All three positions must be able to agree to it
5 / 28

Purpose and setting: practicing Hou-Ren-Sou

  • Purpose: practice Hou-Ren-Sou
  • Report the results
  • Keep each other informed of the present
  • Consult on the plan
  • Ningenryoku Course, MJIIT; December 1 and 2, 2026; rooms of 5 to 6
6 / 28

More than a light source changes

  • Halogen bulb (Part A) to LED (Part B)
  • Driver circuit goes inside the lamp
  • Wiring and connector change on the vehicle
Part A:halogen bulbPart B:LEDLight sourceswapDriver circuitinside the lampVehicle-side wiringand connector
7 / 28

Static makes handling different

  • LED and driver circuit are sensitive to static
  • Handling changes from production to assembly
  • The change reaches the plants' daily work
8 / 28

Control and final inspection need rethinking

  • Vehicle control needs rethinking
  • Plants' final inspection needs rethinking
  • Final inspection means beam aim measurement
9 / 28

Three dates on the calendar

  • Today: Friday, April 16, 2027
  • Dealers by Friday, September 17, 2027
  • Day D: Friday, October 1, 2027
Friday,April 16,2027By Friday,September 17,2027Friday,October 1,2027TodayDisplay andtest-drivevehicles reachdealersDay D,worldwidelaunch24 weeks
10 / 28

The meeting that starts the work

  • Y Electrical's lead coordinator calls it today
  • An all-party coordination meeting
  • Your room prepares for it
  • Three positions must find one path
11 / 28

Timing conditions that bind the schedule

  • New operating calendar at X Motors
  • Plant 1 considering moving its planned stop to the summer holiday
  • Stricter beam aim check in vehicle inspection
  • New rule requiring auto-leveling on headlamps
  • Details: common case on the web tutorial site
12 / 28

Two voices: R&D center and plants

R&D center

  • "Just swap the light source."
  • Drawing: "M6 planned"
  • Formal change notice not issued

Plants

  • "We can't change the line."
  • Lines must keep running
  • Quality must not drop
13 / 28

The suppliers ask questions too

  • Z Electronics and W Precision are asking
  • How long will old-part mass production continue?
  • No molds from a "planned" drawing
  • They wait on a decision, not a guess
14 / 28

"M6 planned" is Planned, not Decided

  • Planned: written on a drawing
  • Decided: formally issued
  • "M6 planned" is Planned
  • Mark every fact on your sheet
Drawing:LED modulefixing screwM6 plannedStatus:PlannedDecidedFormalengineeringchange noticenot issued
15 / 28

Three positions share one room

  • All three positions sit in one room
  • Group 1: X Motors plants
  • Group 2: X Motors R&D center
  • Group 3: Y Electrical (Tier 1)
16 / 28

Lines that each position will not give up

Plants and R&D

  • Plants: the lines do not stop
  • Plants: quality does not drop
  • R&D: LED stays
  • R&D: the electromagnetic noise standard is kept

Y Electrical and all

  • Y Electrical: every decision is recorded
  • Record who decided, and when
  • Everyone: Day D does not move
17 / 28

Agreeing who takes which role

  • Agree among yourselves who takes which role
  • With 6 people, take two per position
  • With 5 people, Y Electrical gets two
  • Y Electrical coordinates, so it gets two
  • Split the plants and the R&D center
18 / 28

A boss who will not hand you answers

  • Your boss is a Veteran AI Boss who talks by voice
  • You call as a new hire on their team
  • The boss will not give you answers
  • Bring a plan with convincing evidence
19 / 28

Three bosses and what each one wants

  • Hiroshi Tanabe: manufacturing section manager, Plant 1
  • Tanabe-san: shop-floor dates and days, document name and date, who decided
  • Mika Asano: chief engineer
  • Asano-san: measured values, formal documents and dates, working back week by week
  • Ryo Kitagawa: lead coordinator
  • Kitagawa-san: who decided, when, in what position, on record, who carries cost and schedule
20 / 28

New information and calls to other positions

  • Your boss knows things not in the common case
  • What your boss tells you is new for your room
  • You may call a boss from another position
  • Speak as that boss's own new hire
21 / 28

Hou-Ren-Sou: communication by time

  • Hou: report the past
  • Ren: inform of the present
  • Sou: consult on the future
  • A time-based rule for communication
22 / 28

Sou: consult before you decide

  • Write your plan in one sentence
  • Then call your boss
  • Ask one clear question
  • Keep each call to about 3 minutes
23 / 28

Hou and Ren: report and inform your room

  • Hou: right after each call
  • Report within 2 minutes
  • Say what the boss said, the evidence, what is open
  • Ren: whenever your situation changes
  • Tell the room before calling another position's boss
24 / 28

The report form and the three status marks

  • Boss: who you called
  • Heard: the point in one sentence
  • Status: Decided, Planned or Unknown, with source
  • Open: what still needs an answer
  • Mark every fact on your sheet
25 / 28

The four items on your preparation sheet

  • Item 1: what changes, and who each change affects
  • Item 2: what must be decided, by when, by whom
  • Item 3: Decided, Planned or Unknown, with sources
  • Item 4: cannot give up, can give up, path to agreement
26 / 28

How the 60 minutes run

  • 0-5 min: introduction
  • 5-15 min: mission and roles
  • 15-40 min: discussion
  • 40-55 min: presentations
  • 55-60 min: wrap-up
05154055600-5 minIntroduction15-40 minDiscussion55-60 minWrap-up5-15 minShare mission,agree roles40-55 minPresentationsminutes
27 / 28

Wrap-up: compare your path

  • Last 5 minutes: wrap-up, minutes 55 to 60
  • Compare your path with the Yamaguchi University students' path
  • Presentations come first, with lecturer comments